§ 122-66. Testing of facilities installed by developers.
Latest version.
Representatives of the county may be present at tests of component parts of water
distribution, reclaimed water distribution or sewage collection systems for the purpose
of determining that the system, as constructed, conforms to the county's criteria
for exfiltration, infiltration, pressure testing, line and grade. Such tests will
be performed by the developer or the developer's contractor, but only under the direct
supervision of the engineer of record or his authorized inspector. The results of
such testing shall be certified by the engineer of record. The utility engineer shall
be notified at least two working days prior to any inspections or testing performed
in accordance with this article.